|

|
Client: Westward Seafoods, Inc.
Owner: Westward Seafoods, Inc.
Cost of Work: $75 million
PND was selected to provide surveys, site-civil, dock, building
structural and foundation design for this state-of-the-art
fish processing complex, which involved extensive meetings
and continued close coordination with a team of Japanese
and American owners. More than 300 design drawings and two
subdivision plats were prepared for this fast-track project
in less than five months.
The
facility is a 100,000-square-foot industrial building
housing surimi and crab processing operations, a meal
plant, and cold storage. Included are a 12,000-square-foot
powerhouse furnishing 4 mega-watts of generator capacity;
a 700,000-gallon fuel tank farm; more than 65,000 square
feet of bunkhouse and townhouse living facilities (five
buildings for 250 workers); a galley capable of seating
250; warehouse and repair buildings; a sheet pile dock
with 650 feet of face; more than 20 acres of uplands
development, encompassing building sites, roads, 150,000
cubic yards of fill behind the dock, and 40,000 cubic
yards of disposal; 24-inch-diameter seawater intakes
and outfall pipes; a 5,500-foot sewer force main, including
a lift station; sewer/water site utilities; and connections
to a 24-inch-dia-meter high-pressure freshwater force
main.
PND surveyors recovered Alaska tideland survey monuments,
tidal benchmarks, and local boundary to define datum
and boundaries. A complete site plan was surveyed to
define contours, upland and ocean bottom, existing facilities,
buildings, roads, and aboveground utilities. Underground
utilities were located by public locates. These were
surveyed and added to base maps in conjunction with as-built
drawings. Various generations of drawings were generated,
including boundary maps, utility drawings, site plans,
utility as-builts, proposed subdivision, and ocean bottom
hydrographic surveys.
PND
prepared and submitted all permits, including those
required by the U.S. Army Corps of Engineers; Environmental
Protection Agency (NPDES - Discharge); Department of
Environmental Conservation (air quality); and Department
of Natural Resources (Tideland Lease). PND coordinated
architectural services for all buildings; managed electrical
mechanical design for support buildings; and reviewed
pre-engineered
metal-building submittals.
Pile
foundations were selected for the industrial, powerhouse,
bunkhouse and galley buildings, due to the poor soil
conditions at the site, while conventional grade beam
and footing foundation design was provided for the 80-
by 100-foot warehouse and for a 40- by 100-foot shop
repair building. After assisting in procurement of the
required sheet piles and foundation piles, PND proceeded
to direct pile-driving activities. In all, more than
450 12-, 16- and 24-inch-dia-meter piles, or approximately
25,000 linear feet of pile, were installed in less than
three months. |