|

|
Client:
Cominco Engineering Services, Ltd.
Owner: Cominco Alaska, Inc. (now TeckCominco)
Cost of Work: $45 million
PND was prime engineering consultant for design of this
major access road in northwestern Alaska, approximately
80 miles north of Kotzebue, extending 54 miles from the
Chukchi Sea to the Red Dog Mine, one of the largest and
richest lead/zinc mines in the world.
PND performed preliminary geotechnical exploration;
located borrow pits; evaluated stream and river hydrology;
assisted with permit filing; and directed area terrain
mapping, performed using photogrammetric techniques.
Based on acquired data, PND designed a road alignment
that maintained close proximity to borrow sources, minimized
the number and size of stream crossings required, and
provided the best foundation.
PND directed field surveys
of the alignment, temporary roads to borrow pits, and the
borrow pits themselves, and concurrently managed production
of plan and profile drawings for alignment. An in-depth
final site assessment, including geotechnical investigation,
hydrology studies, vegetation analysis and slope stability
studies, and soil thaw-depth studies, was completed. More
than 180 test holes were drilled at major stream crossings,
material sources, and road centerline. Hydrologic studies
included field surveys of stream cross sections, runoff
and snow drift depth measurements, and determination of
flood flow characteristics.
Preliminary and final design for the roadway, turnouts,
and all bridges and culverts was provided. To accommodate
1,600-ton mining modules and large ore carriers, the
road has a maximum 4% grade and minimum 600-foot curve
radii. It was set directly on undisturbed tundra cover,
to insulate and protect underlying frozen soils. A minimum
of 4 feet of gravel cover ensured summer thaw would not
reach ice-rich soils below the vegetative mat. High-strength
filter fabric was placed under the road embankment to
resist potential slope failures under heavy loads. Approximately
1.6 million square yards of filter fabric were utilized
- one of the largest applications in the world.
In all, 10 bridges traverse
major drainages. The standardized 40-foot bridges, with
steel piles, steel superstructure and precast concrete deck,
allowed rapid construction. Pile installation incorporated
techniques to accommodate marginally frozen soil and weathered
bedrock. Seven major culvert batteries and 500 minor culverts
totalling over 7 miles were designed. For flexibility, project
specifications were written to make culvert positioning
acceptable either during road placement, or by breaching
the road after pad construction.
|